  1. December 2020 MCCA purchased the Civic Center Garage from the City of Springfield
  2. Spring 2021 MCCA began collaboration with City of Springfield towards adherence to the City’s Master Development of the Convention Center District
  3. Summer 2021 MCCA developed a parking analysis and feasibility study of the location
  4. Fall 2021 MCCA selects Desman/KVA as Design Team for Convention Center Carpark
  5. Spring 2022 Desman/KVA completed demolition documents & developed conceptual design of carpark
  6. Summer 2022 Stamford Wrecking Awarded demolition of Civic Center Garage
  7. Summer/Fall 2022 City of Springfield acquired 22 Bruce Landon Way, MCCA to purchase
  8. Fall 2022 Design Development Documents established for procurement of a Construction Manager
  9. Fall 2022 Daniel O’Connell’s Sons Awarded Construction Project
  10. Winter 2022/23 Complete Design/Establish Project Cost
  11. Spring 2023 Begin foundations & site work
  12. Summer 2024 Project complete/Streetscape Complete